Timing is everything when it comes to applying for a Department of Energy (DOE) SBIR award. Knowing what to expect—and when—can help you manage internal resources, set realistic expectations, and plan around funding gaps. This post walks you through a typical DOE Phase I application timeline, including key deadlines, common waiting periods, and what happens at each stage. Whether you’re a first-time applicant or looking to refine your internal planning, understanding this process will give you a practical edge.
From Pre-Solicitation to FOA Release
The DOE SBIR application process begins well before the full solicitation is released. In the pre-solicitation phase, DOE publishes a list of upcoming topics—typically about a month before the Funding Opportunity Announcement (FOA) goes live. This early release gives small businesses a chance to review topic areas, assess alignment with their technology, and reach out to topic managers with questions.
This is the best window to seek clarification or confirm whether your concept fits within a given topic. Once the FOA is issued—usually in early December for Release 2—the communication window closes, and DOE program officials can no longer provide guidance.
The FOA marks the official launch of the application process. From that point, the deadlines are fixed and fast-moving, starting with the Letter of Intent just a few weeks later.
Letter of Intent (LOI) Stage
Roughly three weeks after the FOA is published, the DOE requires a Letter of Intent (LOI) from all prospective applicants. While the LOI itself is short—typically just a brief description of your proposed project—it serves a critical function. It allows DOE to begin identifying and assigning reviewers in advance, streamlining the review process once full proposals are submitted.
You’ll need to submit your LOI through the Portfolio Analysis and Management System (PAMS). Missing this deadline means you won’t be allowed to submit a full application, so treat it as non-negotiable. There’s no peer review at this stage, but DOE may reject an LOI that is deemed non-responsive to the topic, and you’ll be notified if that’s the case.
This early checkpoint ensures alignment with DOE’s goals and helps filter out proposals that clearly fall outside the scope of current topic areas.
Full Application Phase
Once your LOI is accepted, the next step is submitting your full application—typically due about six to eight weeks later. This is where the bulk of your effort goes. You’ll need to prepare a detailed technical proposal, budget, commercialization plan, and supporting documents.
All DOE SBIR applications are submitted through Grants.gov. This system has strict formatting rules and submission deadlines—proposals must be submitted by 11:59 PM Eastern on the due date. It’s highly recommended that you start the upload process at least a day or two early. Grants.gov can be finicky, and technical issues have derailed many last-minute submissions.
During this phase, stay focused on aligning your proposal tightly with the DOE topic, presenting a clear R&D plan, and justifying your budget. If you haven’t already, this is also the time to confirm registrations (like SAM and SBA Company Registry) are active and error-free.
Review & Selection Period
After the application deadline passes, the DOE moves quickly into review mode. Because reviewers have already been identified during the LOI stage, evaluations begin almost immediately. This stage typically spans two months.
Your proposal will be assessed on several criteria, including scientific and technical merit, the qualifications of your team, and the potential for commercialization. Depending on the topic, your application may go through both individual peer reviews and panel discussions.
About 90 days after the submission deadline, DOE sends out award notifications. If you’re selected, you’ll receive an official email and next steps from the agency. If you’re not selected, expect a notification around the same time. While delays are possible, the agency is generally good at meeting this 90-day benchmark.
If You’re Selected: Contracting and Kickoff
Being selected for a DOE SBIR award is a significant milestone—but there’s still work to do before you can begin. Over the next 4 to 8 weeks, you’ll finalize grant paperwork with DOE’s contracting office. This includes verifying business eligibility, submitting final budgets, and resolving any compliance requirements, such as human or animal research protocols if applicable.
Once everything is approved, you’ll receive a formal grant agreement outlining your project’s start date, budget, and performance period. Many Phase I projects begin at the start of a calendar month. For example, a Release 2 applicant might begin July 1, while a Release 1 project could start around April 1.
DOE often hosts a kickoff webinar for new awardees. It covers how to request drawdowns (DOE SBIR funds are grants, not upfront payments), what reporting is required, and who to contact for technical and administrative questions.
If You’re Not Selected: Feedback & Next Steps
Not every application gets funded—and that’s okay. If your proposal isn’t selected, the DOE will send a formal notice of decline. In many cases, you’ll also receive reviewer comments. These often include summary statements with noted strengths, weaknesses, and average scores for each review criterion.
This feedback can be invaluable. It helps you identify where your proposal fell short and what could be improved for future submissions. Occasionally, you may need to request the reviewer feedback explicitly—be sure to check the decline notice for instructions.
If you don’t receive any comments, it’s acceptable to politely contact the DOE SBIR program office and ask whether feedback is available. Keep in mind that a rejection doesn’t necessarily mean your idea lacked merit. Many applicants succeed only after revising and resubmitting in later cycles.
The Phase I Period
Once your project officially starts, you’ll enter the Phase I performance period, which typically lasts between six and twelve months depending on the topic. For DOE, nine months is a common duration.
During this time, your focus is on executing the R&D plan proposed in your application. That includes conducting experiments, validating feasibility, and generating preliminary data. You’ll also need to manage your budget carefully and keep accurate records of all expenditures and technical work.
Periodic progress reporting is required. You may be asked to submit interim updates or check in with your DOE program manager. At the end of the project, a final technical report is mandatory. This report is crucial—it serves as both a record of results and a foundational document if you plan to pursue Phase II funding.
Preparing for Phase II
As your Phase I project nears completion, it’s time to look ahead. Only Phase I awardees are eligible to apply for Phase II, and the DOE typically releases a Phase II FOA during the final quarter of the Phase I performance period.
The Phase II application builds on your Phase I results. You’ll need to present technical outcomes, updated commercialization plans, and a robust R&D strategy for scaling or prototyping your innovation. DOE Phase II awards are significantly larger—often around $1.1 million—and cover up to two years of work.
Use Phase I wisely to gather the data and relationships that will strengthen your Phase II case. That might mean engaging potential customers, refining your business model, or developing early partnerships. DOE also offers TABA (Technical and Business Assistance) to help you prepare for this next stage.
Final Thoughts & Planning Tips
Successfully navigating the DOE SBIR timeline requires more than just meeting deadlines. It demands careful planning—especially during the long stretches between submission and award. Remember, there’s no funding during the proposal phase or the review period, so it’s essential to plan your finances accordingly.
For companies banking on SBIR funding to advance critical R&D, understanding the 6–8 month lag between FOA and award start is key. If you’re applying in February, your project might not begin until summer or fall. Keep your internal timeline aligned with DOE’s cycle to avoid resource gaps or delays.
For first-time applicants, don’t be discouraged by the complexity or competitiveness. Each cycle is an opportunity to improve, and even a declined proposal can be a stepping stone to future success. With a strategic approach and realistic expectations, the DOE SBIR program can become a powerful funding path for your innovation.